The park staff accomplish a great deal to keep Lafreniere beautiful and well-maintained year-round. Their tireless efforts sometimes go unnoticed, but the results are appreciated by hundreds of thousands of visitors each year.  This is a listing of some of the improvements and significant maintenance projects which have been and are currently being undertaken.

Facebook IconFollow Us on Facebook for frequent updates on what's going on at Lafreniere Park!


Pavillion - June 2009
Power washed Pavillion

Start Date:6/1/2009
Complettion Date:6/30/2009


Fence Improvements
Park Perimeter Improvements

Start Date:5/6/2009
Complettion Date:


Foundation Center Equipment
Kitchen and deck equipment

Start Date:5/1/2009
Complettion Date:12/30/2009

July 2009-Installation of double ovens in the kitchen within new cabinet Sept 2009 - ordered 6 benches and 2 trash cans for deck area Dec 2009 - Installed benches & trash cans


Storage Facility
Design and construction of a new storage building

Start Date:5/1/2009
Complettion Date:


Roofing Work
Repair of 3 roofs in Park

Start Date:5/1/2009
Complettion Date:


Walking Track May 2009
Repair of cracks in track

Start Date:5/1/2009
Complettion Date:


ADA Port-O-Lets May 2009
Ordered 2 ADA Port-O-Lets to be placed on either side of the Park

Start Date:5/1/2009
Complettion Date:5/30/2009


Patio Gardens Spraying
Lobbs will spray 6 times per year

Start Date:5/1/2009
Complettion Date:


Gazebo Brick Apron
Addition of a new brick apron in front of the small gazebo near the office

Start Date:4/1/2009
Complettion Date:4/30/2009


Picnic Tables
Installed Ten new picnic tabls under various shelters

Start Date:4/1/2009
Complettion Date:4/30/2009


Entrance Gate
Repaired Downs Blvd Entrance Gates

Start Date:4/1/2009
Complettion Date:4/30/2009


Water Fountains
Installed two new water fountains which were donated by the New Orleans Track Club

Start Date:4/1/2009
Complettion Date:4/30/2009

New Orelans Track Club


West Napoleon Fencing
Repair and replacement of perimeter fencing along West Napoleon property line

Start Date:4/1/2009
Complettion Date:9/30/2009

In Sept 2009 - Began in-house repairs to sub-surface supports. Filled low spots with limestoneand pump sand


Fill Added
Filled low spots within the park grounds

Start Date:4/1/2009
Complettion Date:4/30/2009


Water Line near Bathroom #4
Repair of water line near bathroom #4

Start Date:4/1/2009
Complettion Date:4/30/2009


Bird House
Installed Purple Martin bird house

Start Date:4/1/2009
Complettion Date:4/30/2009


Chin-up Bar
Repaired chin-up bar in West Napoleon fitness station

Start Date:4/1/2009
Complettion Date:4/30/2009


Christmas Lights
Lighting display includng lights from the Copeland's

Start Date:4/1/2009
Complettion Date:

July 2009 - directional boring planned for electrical work


Ranger Station
Removal and Replacement of Rangers Station

Start Date:4/1/2009
Complettion Date:4/1/2009


Fitness Station Repair
Repaired Chin Up bar on W. Napoleon Station. Repaired other equipment

Start Date:4/1/2009
Complettion Date:6/30/2009


Dog Park
Design and Building of a Dog Park within the park

Start Date:3/1/2009
Complettion Date:

Survey complete - Under design


Concession Stand
Concession stand improvements

Start Date:2/1/2009
Complettion Date:2/1/2010

Extended deck on north side of Concession. Updated plumbing in concession. Replaced A/C unit. Installed shutters. Replaced appliances. Installing fire suppression system. Installed new handrails. Planted hedges around concession


Health Track Lighting
Improvements to Health Track lighting

Start Date:1/1/2009
Complettion Date:4/30/2009


Holiday Lighting Improvements
Acquisition and installation of select Holiday Lighting from the collection of Al Copeland

Start Date:1/1/2009
Complettion Date:


Carousel Tot Lot Safety Surface
Repaired safety surface in carousel tot lot as per warranty

Start Date:4/1/2000
Complettion Date:4/30/2009